Allseas Launches Echo in China, First of Two New Offshore Construction Vessels
Cubierto por 3 fuentesPublicado
Allseas launched the Echo, the first of two new offshore construction vessels (OCVs), at the Wuchang Shipbuilding Industry Group facilities in Wuhan, China. The sister vessel, named Pulse, remains under construction at the same shipyard.
The launch operation
After months of hull assembly and outfitting, the shipyard used its side-launch platform to transfer the Echo into the water. According to Allseas, the maneuver took around four hours, including a pause to check the hull's watertightness, until the vessel was fully afloat. From now on, the Echo will remain alongside the shipyard's quay, where most of the commissioning work and systems testing will be carried out before delivery.
Technical specifications
The Echo and its sister vessel Pulse are based on a Salt Ship Design, measuring 100 meters in length overall and 23 meters in beam, with DP2 dynamic positioning. Both vessels will feature a 150-tonne offshore crane with active heave compensation, a hangar for two work-class remotely operated vehicles (ROVs) capable of operating at depths of up to 4,000 meters, and a 1,500 kWh battery energy storage system. The propulsion system is methanol-ready.
Schedule and purpose
Allseas signed the contracts to build both vessels in April 2025, when deliveries were originally scheduled for September and December 2026. The company now projects delivery of the first vessel for the fourth quarter of 2026 and the second for the first quarter of 2027. The vessels will carry out subsea construction and intervention work, decommissioning, ROV support, and inspection, maintenance and repair tasks, with the aim of freeing up Allseas' current construction vessels for larger-scale projects.