ANPYN Extends Intervention at Port of Ushuaia, Approves Works Plan
Cubierto por 3 fuentesPublicado
The National Ports and Navigation Agency (ANPYN) extended the administrative intervention at the Port of Ushuaia and approved an Infrastructure Works Plan for the terminal. The decision was formalized in Resolution 69/2026, signed on November 18, which makes the continuation of the measure conditional on completion of the planned works and on guaranteeing minimum services and port security.
Signature and effective date
The resolution was signed by ANPYN's executive director, Iñaki Arreseygor, and takes effect on November 19. The measure extends the intervention ordered on January 20, 2026 for an initial twelve-month period, but does not set a new end date: its continuation remains subject to progress on the approved works plan.
Reasons for the extension
According to the grounds set out in the resolution, the irregularities detected during the second half of 2025 were not fully resolved. ANPYN cited structural deterioration of the commercial dock, safety and maintenance shortcomings, failures in environmental pollution control, and the diversion of port activity funds to unrelated purposes.
Planned works
The plan provides for replacing fenders on the commercial dock, structural repairs at berths 3 and 5 and on the front of berth 1, expansion of the electrical and water networks, and the refloating of the Argentine Navy's Yerba-3 floating dock, which sank at berth 3. In the catamaran sector, plans call for upgrading the current dock, repairing a pontoon, and moving forward with the tender for a new 120-meter concrete dock, while the container yard is slated for electrical upgrades for reefer containers, a new perimeter fence, and repaving. The fender replacement began in September 2026 according to comex online and Argen Ports, although Data Portuaria notes that the work actually started in October, with completion estimated for May 2027.
Progress and pending items
ANPYN declared completed the multimodal infrastructure survey, the regularization of land titles, and the maintenance of backup electrical systems, as well as certifications such as pest control (deratization), the ISPS Code certificate, and water potability. Among the matters still being monitored are the port security audit before the Naval Prefecture, the renewal of the camera system, and the integration of operating and accounting systems. Argen Ports specified that the works schedule runs through June 2028, when repairs to the operating surface of the commercial dock are expected to be completed.