APM Terminals and Port of Rotterdam Authority advance Maasvlakte II expansion
Cubierto por 4 fuentesPublicado
- APM Terminals Maasvlakte II and Port of Rotterdam Authority take next step in terminal development
- APM Terminals Maasvlakte II impulsa la expansión de la terminal de contenedores de Róterdam
- APM Terminals Maasvlakte II and Port of Rotterdam Authority take next step in terminal development
- APM Terminals y la Autoridad Portuaria de Róterdam impulsan la expansión de Maasvlakte II
- APM Terminals plans to add 1.4m TEU a year at port of Rotterdam
APM Terminals Maasvlakte II and the Port of Rotterdam Authority announced they are advancing a new expansion phase of the container terminal located at Maasvlakte II, within the Port of Rotterdam. The expansion will add 25 hectares of terminal area, around 711 additional metres of quay and 1.4 million TEU of annual capacity once completed.
Infrastructure works
The Port of Rotterdam Authority will build a new quay wall along the Prinses Amaliahaven, extending the existing quay by 711 metres and the landside crane rail by 428 metres. The works also include dredging approximately 1.3 million cubic metres of sand, which will provide additional capacity for deep-sea, feeder and inland vessels.
Division of responsibilities
Under the agreement between the parties, APM Terminals Maasvlakte II will be responsible for developing the terminal operations, while the Port of Rotterdam Authority will carry out the required maritime infrastructure. Harold Kunst, Managing Director of APM Terminals Maasvlakte II, said the expansion marks the next step in the terminal's long-term development and that collaboration with the port authority is essential to lay the groundwork for this new stage. For his part, Boudewijn Siemons, CEO of the Port of Rotterdam Authority, highlighted that the investment in additional capacity and modern infrastructure strengthens Rotterdam's position as Europe's leading container port and the resilience of logistics chains.
Expected timeline
In the coming months, both parties will define the technical scope, timeline and procurement strategy. The investment decision by the shareholders of the Port of Rotterdam Authority is expected in February 2027. The prequalification process will be published on TenderNed in January 2027, with the tender award phase for the quay wall construction expected in March 2027, while construction of the expansion will take place between October 2027 and January 2030.