APS Invests R$99.1 Million in Structural Reinforcement of Ilha Barnabé Wharf
Cubierto por 3 fuentesPublicado
The Santos Port Authority (APS) has begun mobilization for the rehabilitation and structural reinforcement works on the Ilha Barnabé wharf, located on the left bank of the Santos estuary. The project, carried out by Consórcio IBSA, requires an investment of R$99.1 million and has a 21-month execution period.
Timeline of works
The work order was issued on October 23 and authorized the installation of the site facilities at the location. The preparatory phase is expected to conclude and actual intervention work at Cais São Paulo is scheduled to begin in early 2027.
Scope of work
The engineering work includes reinforcing the wharf structure, restoring soil retention, and replacing the fenders that cushion vessel contact with the quay during berthing. A new mooring dolphin will also be built, and oil containment and environmental protection systems will be installed. According to APS, the works will not interfere with navigation in the channel, and temporary restrictions will be limited to the work areas.
Operational importance
Ilha Barnabé handles liquid bulk fuel and chemical operations at the Port of Santos, and its terminals, together with others in the segment, moved around 16.3 million tons in 2025. Through this restructuring, APS aims to preserve the existing infrastructure, extend the wharf's service life, and improve operating conditions for vessels using the facility.
Environmental monitoring
The Brazilian Institute of Environment and Renewable Natural Resources (Ibama) classified the works as an activity not subject to environmental licensing. Despite this exemption, APS stated that execution will follow protocols to prevent, mitigate, monitor and control potential impacts, including risk management, environmental quality monitoring, aquatic life tracking, sediment control, and communication with surrounding communities.