Bahía Blanca to Invest US$200 Million to Deepen Its Maritime Access Channel
Cubierto por 3 fuentesPublicado
The governor of Buenos Aires province, Axel Kicillof, announced on November 25 a US$200 million investment to deepen the navigation channel of the estuary providing access to the port of Bahía Blanca. The project's main goal is to expand the port system's capacity to export oil from Vaca Muerta, allowing Suezmax tankers operating out of Puerto Rosales to sail at full load.
Project Details
The works will raise the operational draft from 45 to 51.5 feet (from 13.7 to 15.7 meters) along more than 100 kilometers of channel, from buoy 21 toward the outer stretch. The board of the Bahía Blanca Port Management Consortium approved the project, which also includes hydrocarbon storage and dispatch works to be carried out by an Oiltanking terminal. The dredging tender, won by a joint venture between Jan De Nul and Compañía Sudamericana de Dragados, sets a cap of US$97 million for the channel deepening, with a twelve-month timeframe from the formal start of works, plus fifteen years of maintenance dredging. According to sources consulted by Argenports, the works would begin between February and March 2027 and would take ten months to complete.
Impact on Freight Costs
Kicillof noted that vessels currently sail at 70% of capacity, which drives up freight costs, while Guillermo Blanco, vice president of terminal operator Otamérica, placed outbound Suezmax loads between 80% and 85% of capacity. With full loads, freight cost per barrel could drop between 15% and 20% according to Blanco's figures, or by as much as 30% according to Kicillof's, provided the total freight cost per vessel and voyage remained unchanged.
Benefit for Bulk Carriers
The project will also ease tide-related waiting times for bulk carriers loading at Ingeniero White, within the same estuary. Currently, if the tide begins to drop before transit is completed, these vessels may be forced to anchor for up to eight hours. With greater depth in the outer stretch, bulk carriers and tankers—which share the same tidal window to navigate with a 45-foot draft—will have more under-keel clearance, making it easier to coordinate departures without grain shipments bearing the cost of the deepening.
According to data cited by Blanco, Asia and Oceania already receive between 30% and 35% of crude oil exports from Puerto Rosales, which total around 330,000 barrels per day, while roughly half is bound for the Gulf of Mexico and the Caribbean. Looking ahead, the Vaca Muerta Oil Sur terminal in Punta Colorada is designed to receive VLCCs with cargoes of approximately two million barrels; its CEO, Gustavo Chaab, estimates that the first tanker will load there by late March or early April 2027.