Cádiz Joins the Two Sections of the Access Tunnel to the New Container Terminal
Cubierto por 4 fuentesPublicado
- El Puerto de Cádiz culmina la conexión entre los dos tramos del túnel de acceso a la Nueva Terminal de Contenedores y afronta la recta final de las obras
- Puerto de Cádiz conecta los dos tramos del túnel de la Nueva Terminal de Contenedores
- Cádiz conecta el túnel de acceso a la Nueva Terminal de Contenedores
- Infraestructuras portuarias. El túnel de acceso a la Nueva Terminal de Contenedores de Cádiz ya está conectado en toda su longitud
The Bahía de Cádiz Port Authority (APBC) completed this week the connection between the two sections into which the access tunnel to the New Container Terminal (NTC) had until now been divided. Over the past two and a half months, the remaining 150 meters of material separating both sections—around 10,000 cubic meters—were excavated using mining methods, achieving one of the key milestones of this strategic infrastructure for the port of Cádiz. Following a site visit, the Port Authority confirmed that the tunnel is now connected along its entire length.
Timeline and features of the roadway
According to APBC forecasts, the civil works will be completed by summer 2027, with all tunnel installations finished in the last quarter of that year. The roadway, which will connect the New Container Terminal with Avenida de Astilleros, has a total length of 1.2 kilometers, of which 870 meters run through the tunnel, largely beneath land granted under concession by the Port Authority to Navantia Reparaciones Cádiz. Remaining work in the connection area includes lowering the excavation level to build the lower reinforced concrete slab that will close off the structure.
A Project Marked by Problems Since 2014
Work on the tunnel began in November 2014 and faced significant technical difficulties. The Port Authority terminated the original contract in June 2017 due to various problems that arose during construction, after the portion of the tunnel built up to that point became completely flooded. Since May 2019, the APBC has carried out works to recover the infrastructure, repairing the water leaks that kept it flooded, draining it, and stabilizing sections at risk of deterioration, in addition to completing a jet grouting treatment behind the diaphragm walls and micropiles to ensure the durability of the structure.
Remaining Work and Surrounding Area
The project is now entering its final stage, which includes completing the civil works, interior paving, installation of the tunnel's systems, surface road works to adapt to Navantia's infrastructure, and other ancillary works. In parallel, the Port Authority is working on the redesign of the Los Bomberos roundabout, where the tunnel entrance will be located, which must be adapted both to the new port connection and to the future widening of Avenida Industrial, to be carried out by the City Council.
The tunnel addresses the need to reconcile the heavy vehicle traffic that the New Container Terminal will generate once fully operational with the activity of the Cádiz shipyard. The structure also carries the freight rail platform that will serve the new terminal, another strategic piece of infrastructure aimed at boosting intermodality at the Port of the Bahía de Cádiz.