Galveston Approves Modular LNG Plant on Pelican Island with Power LNG
Cubierto por 3 fuentesPublicado
The Galveston Wharves Board of Trustees approved a lease and development agreement with Power LNG to build a small-scale modular liquefied natural gas production, storage and bunkering facility on Pelican Island, within the Port of Galveston. The agreement was approved at the October 8 meeting, and commercial production is expected to begin in the fourth quarter of 2028, once the necessary approvals and agreements have been obtained.
Capacity and planned works
The plant will have initial capacity to produce approximately 400,000 gallons of LNG per day through two parallel liquefaction trains of 200,000 gallons per day each, with the potential to expand production to 800,000 gallons per day using modular liquefaction technology. The development will occupy 30 acres of undeveloped land on the eastern section of an approximately 82-acre port site on the Galveston deepwater port, and will include an underground pipeline to supply feedstock to the facility, an LNG storage tank with capacity for 3 million gallons, and a shore-to-ship dock to bunker both vessels and LNG fuel supply ships.
Statements from executives
Rodger Rees, Port Director and CEO of Galveston Wharves, noted that the agreement allows the port to take a leading role in supplying cleaner marine fuels for the region, creating jobs and helping improve air quality. Rees added that, as more LNG-powered vessels are built, demand for this marine fuel is reaching a critical point, and that the facility will give Galveston the opportunity to support that growing market while diversifying port operations. For his part, Austin Terry, CEO of Power LNG, highlighted that the company will develop a comprehensive LNG supply solution that includes liquefaction, storage, bunkering, ship loading and export capabilities.
Broader port plan
According to Maritime Executive, this would be the first LNG bunkering facility on the Gulf Coast, and it is part of Galveston Wharves' plan to develop Pelican Island, one of the few large-scale deepwater port sites still underdeveloped in Texas, where the port owns 357 acres of waterfront land, including 100 acres next to the Gulf Copper shipyard that Davie Defense is converting into a facility for building Arctic icebreakers and other projects. The port had already highlighted in early 2024 that it was one of the first in the United States to offer LNG bunkering services to vessels, a strategic advantage for attracting cruise lines such as Carnival Cruise Line and for meeting demand from container ships and tankers.
Future expansions
As part of the long-term development, the port and Power LNG plan to negotiate agreements for LNG and ISO tank container loading operations at a future port-owned dock adjacent to the leased property. The parties also anticipate future LNG-related activities in other port areas, including ISO container loading and export operations in sections of Pier 34 and truck-to-ship LNG bunkering in parts of Pier 39.
Más destacadas
Holland America Opens Bookings for First Voyages of Revamped OosterdamHolland America Line has opened bookings for five new voyages aboard the Oosterdam, set to begin on October 31, 2027, following the ship's Evolution transformation in Marseille, France, which will add new suites and spaces such as the Grand Dutch Café.
Port de Barcelona and Red Eléctrica Move Forward on Port DecarbonizationThe Port de Barcelona and Red Eléctrica are jointly advancing the port's Energy Transition Plan, electrifying berths through OPS systems and connecting the Cerdà and Port substations, which provides 80 MW of electrical capacity to advance toward green methanol and hydrogen.
Golar LNG Buys Grace Dahlia Carrier for Its Fourth MkII-Type FLNGGolar LNG has acquired the LNG carrier Grace Dahlia, the world's largest Moss-type vessel, to convert it into its fourth FLNG unit, the second of MkII design, ordered in August from CIMC Raffles in China with delivery expected in 2029.
APM Terminals Callao to Invest US$231 Million in New Berth 5CAPM Terminals Callao will build Berth 5C, measuring 440 meters long and 16 meters deep, with an investment of US$231 million. The project, expected to be completed by January 2028, will expand the North Terminal's capacity to 1.7 million TEU per year, with potential for up to 2.2 million.