Germany Opens Fourth Floating LNG Terminal in Stade, Three Years Behind Schedule
Cubierto por 3 fuentesPublicado
German state-owned company Deutsche Energy Terminal (DET) launched its floating liquefied natural gas import terminal in Stade, in the state of Lower Saxony, on Monday, November 16, nearly three years behind the original timeline set by the Federal Ministry for Economic Affairs. The start-up was confirmed both by the news agency covering the event and by trade media outlets that reported DET's announcement.
Operational details
The terminal uses the floating storage and regasification unit (FSRU) Energos Force, a 294-meter vessel built in 2021, owned by Energos Infrastructure and chartered by DET, moored at a dedicated energy berth at the Stade-Bützfleth industrial port. The facility is expected to supply up to 3,200 million cubic meters of natural gas to the German transmission grid during 2027, a figure DET described as the maximum technically achievable throughput under ideal conditions. Federal Minister for Economic Affairs and Energy Katherina Reiche attended the inauguration ceremony.
A delayed project
The project was originally scheduled to enter service in December 2023, but was delayed due to disagreements between DET and its infrastructure partner Hanseatic Energy Hub (HEH) over the completion and acceptance of the onshore facilities. During the delay, the Energos Force was temporarily subchartered to Egypt's EGAS and deployed to Jordan, before returning to Stade in September 2026. Start-up was further postponed until 2026 after DET took over, in November 2025, completion of the terminal's superstructure, a task previously assigned to HEH.
First cargoes and next steps
The commissioning process followed the arrival on November 2 of the French-flagged LNG carrier Lech Kaczyński, chartered by Polish energy company ORLEN, which arrived with approximately 160,000 cubic meters of LNG from the Plaquemines export terminal in Louisiana, United States. DET plans to auction storage, regasification and grid send-out capacity for the first quarter of 2027 on November 19. The Stade terminal will remain in operation until HEH's permanent onshore facility enters service in 2029.
Energy context
Stade becomes Germany's fifth floating LNG terminal and the fourth operated by DET, which also manages two terminals in Wilhelmshaven and one in Brunsbüttel; the company projects total send-out of at least 98.8 TWh in 2026, equivalent to about 8,670 million cubic meters. According to data from Gas Infrastructure Europe, Germany's gas storage was 59% full as of November 9, compared with a European Union average of 72.4%. German environmental organization Deutsche Umwelthilfe criticized the inauguration over reliance on US shale gas and called for a moratorium on new LNG infrastructure.
Más destacadas
Höegh Autoliners and LOTTE Fine Chemical Agree on Marine Ammonia Supply Deal
Hanwha Successfully Test-Fires Chunmoo Missile From Ship Off Mississippi Coast
Grupo Alonso Acquires UAE-Based Cargo Line, Expanding Its Network in the Middle East
Seatrium to Integrate FPSO Essequibo 1899 for Hammerhead Project in Guyana