Mindanao Container Terminal Adds RTG Cranes, Advances Quay Expansion
Cubierto por 2 fuentesPublicado
Mindanao Container Terminal (MCT), the International Container Terminal Services, Inc. (ICTSI) operation serving trade in the northern part of the Philippine island of Mindanao, is expanding its capacity to meet growing cargo demand and additional shipping services. The arrival of four hybrid rubber-tired gantry (RTG) cranes marks the latest step in an expansion program that includes a 300-meter quay extension, orders for three post-Panamax quay cranes, expanded refrigerated container facilities, and increased container storage capacity.
Project Timeline
Aurelio C. García, MCT's chief executive officer, noted that the project was formalized in late 2024 with a clear timeline that remains on track. The RTG cranes arrived approximately three months ahead of schedule, which García considers an important milestone in the terminal's expansion. Construction of the quay extension is progressing according to plan, with the first 120 meters expected to be completed by the end of the first quarter of 2027.
New Infrastructure
The first of the three new post-Panamax quay cranes is expected to arrive shortly after that first phase is completed and to become operational following commissioning. Once this initial stage is finished, MCT's operational quay length will increase to 420 meters, providing additional capacity for vessel calls and shipping services. The expansion also includes the enlargement of refrigerated container facilities, the extension of the empty container depot, and the construction of a new electrical substation to power the additional equipment.
Next Steps
Located in the Phividec Industrial Estate, MCT is the main international container gateway for northern Mindanao, connecting businesses in the region with domestic and international markets. García highlighted that the arrival and commissioning of the first RTG crane was a significant milestone reflecting the project's progress. The terminal's long-term expansion program is scheduled for completion in the first quarter of 2028, when the full 300-meter quay extension and the three quay cranes are expected to be fully operational.