Modec and Shell Complete FPSO Gato do Mato Hull Mating Ahead of Schedule
Cubierto por 3 fuentesPublicado
Modec and Shell announced the completion of the hull section mating works for the FPSO Gato do Mato, the floating production, storage and offloading unit that will operate in the Orca field, in the Santos Basin, in Brazil's pre-salt area. According to agência infra, the milestone was achieved nearly a month ahead of the original schedule, while Portal Portuario and Jornal Portuário also noted that Modec completed the assembly ahead of schedule.
The Gato do Mato is the first Modec unit whose hull sections were built simultaneously at different shipyards, using a modular construction model. The mating and welding works began in October 2026.
Process Details
Portal Portuario reported that the hull mating at the waterline was completed a week ahead of schedule, with a 99% acceptance rate in dimensional control inspections. In late October, the vessel entered dry dock to complete additional tasks, including underwater hull welding, installation of the riser support structure, dimensional checks, and drift and deck removal tests.
Modec's Perspective
Soichi Ide, Director of Modec's Floating Production Solutions Business Unit, noted that early collaboration with partners and coordination with the client during the preparation phase were key to achieving this milestone. Ide explained that one of the main challenges was maintaining dimensional control across multiple shipyards, which was addressed by combining the quality management practices of the Japanese shipbuilding industry with the capabilities of COSCO, its Chinese shipyard partner, under a 20-year strategic alliance. He also thanked Shell for trusting Modec and this approach, as the first client to adopt it.
Goals of the Modular Model
According to Modec, the multi-shipyard modular construction model was adopted to optimize shipyard capacity utilization, increase flexibility in project execution, and reduce the risk of delays in building units intended for deepwater operations. The company noted that this approach is designed to remove hull construction from the critical path of a typical deepwater project and that it plans to apply the lessons learned to future projects.