Mozambique Approves Revised Rovuma LNG Plan with Higher Capacity and Investment
Cubierto por 3 fuentesPublicado
Mozambique's Council of Ministers approved a revised development plan for ExxonMobil's Rovuma LNG project, raising the planned liquefaction capacity from 15.2 to 18.6 million tonnes per annum, a 22% increase over the original 2019 plan. Splash 247 and Ports News Russia cite an estimated investment of $26 billion, while Trade News puts the figure at $30 billion.
Technical Changes
The revised design incorporates electrically driven gas processing and liquefaction modules, aimed at reducing construction costs and cutting emissions by approximately 40% compared to the original plan. The configuration provides for 12 onshore liquefaction trains and 18 subsea wells connected by pipelines and manifolds, processing gas from the offshore Area 4 in the Rovuma Basin. First production is still targeted for 2031.
Economic Impact
The National Petroleum Institute estimates the project could generate $121 billion in state revenue over 25 years of production. The plan also envisages around $6 billion in contracts for Mozambican suppliers, reserves 25% of gas production for the domestic market, and assigns the state-owned Empresa Nacional de Hidrocarbonetos the marketing of all condensate output.
Next Steps
The approval comes after the August selection of a consortium led by Saipem, together with McDermott, Daewoo Engineering & Construction and China Petroleum Engineering & Construction Corporation, for preliminary engineering and procurement work. ExxonMobil, which in October agreed to raise its stake in Rovuma LNG to 50% by taking over part of Eni's position, is aiming for a final investment decision by the end of 2026, which remains pending. The final investment decision is expected next month, according to Trade News.
Regional Context
The approval followed a November 16 meeting between Mozambican President Daniel Francisco Chapo and executives from ExxonMobil and Eni, at which ExxonMobil's upstream president, Dan Ammann, reaffirmed the goal of closing the investment decision before year-end. The regulator's chairman, Nazário Bangalane, said the amendment stemmed from a technical and economic review involving ministries, fiscal authorities and the central bank. Eni separately operates the Coral-Sul FLNG project in the same area and plans to start production from a second unit, Coral Norte, from 2028, while the TotalEnergies-led Mozambique LNG project remains delayed due to security issues.
Más destacadas
Port of Rijeka Awards Shore Power Installation Contract to Končar
Argentina and Fincantieri Sign Letter of Intent for Up to Three FCX20 Corvettes
Valenciaport: Container Traffic Falls 0.71% While Vehicle Shipments Rise 10.87% Through October
Yangzijiang Revives US$506 Million Clean-Energy Shipyard Project in Taicang