Petronas and Staatsolie Approve $1.6 Billion KrakaWi FLNG Project in Suriname
Cubierto por 3 fuentesPublicado
Petronas and Suriname's Staatsolie announced the final investment decision for the offshore gas development known as KrakaWi, a project valued at US$1.6 billion that will develop the Sloanea field in Block 52, off the coast of Suriname. First production is expected in the first half of 2030, and the development will include a floating liquefied natural gas (FLNG) facility.
Field Details
The project envisages four subsea production wells tied back to an FLNG facility with capacity to produce around 1.5 million tonnes of LNG per year, with an estimated operational life of 25 years. According to Splash 247 and Ports News Russia, the field holds estimated recoverable gas resources of 97 billion cubic meters, while Petronas CEO Tengku Muhammad Taufik, cited by Baird Maritime, stated that the development contains around four trillion cubic feet of gas resources, including estimated reserves of two trillion cubic feet. Petronas operates Block 52 with an 80% stake, while Staatsolie holds the remaining 20% through Paradise Oil Company.
Financing and Tax Benefits
Staatsolie will fund its approximately US$320 million share through an existing credit facility. According to Ports News Russia, the project will use an existing FLNG unit rather than building a new one, which avoided raising the total cost to around US$3.5 billion, as estimated by Staatsolie's managing director, Annand Jagesar. The development will enjoy a tax exemption of up to ten years, and Suriname will receive royalties of 6.25% on production, in addition to a share of profit gas and dividends from Staatsolie's stake, which, according to Jagesar, could generate more than US$6 billion for the country over 25 years, depending on international gas prices.
Project Background
The announcement was made on November 26 at the presidential palace in Paramaribo, in the presence of Surinamese President Jennifer Geerlings-Simons and Vice President Gregory Rusland. Gas was discovered at the Sloanea-1 exploration well in 2020, followed by the Sloanea-2 appraisal well drilled in 2024, and the field was declared commercial in November 2025. Staatsolie approved the field development plan on November 24, 2026. KrakaWi will be Suriname's first offshore gas project and the first FLNG facility in the Guyana-Suriname basin.
Regional Context
The development will complement the US$10.5 billion GranMorgu offshore oil project led by TotalEnergies and APA Corporation in Suriname. Petronas is also drilling two exploration prospects in Block 66, with potential resources of around 1 billion barrels of oil equivalent, against a backdrop in which neighboring Guyana has already surpassed 900,000 barrels per day in oil production, prompting Suriname to pursue offshore gas and crude developments of its own.