Port de Barcelona and Red Eléctrica Move Forward on Port Decarbonization
Cubierto por 3 fuentesPublicado
The Port de Barcelona and Red Eléctrica are working together to roll out the projects included in the port authority's Energy Transition Plan, with the aim of decarbonizing berth operations and transforming the port's energy model. The initiative seeks to turn the Port de Barcelona into a hub for the production and distribution of sustainable energy, extending the energy transition beyond port boundaries.
Connection Between Cerdà and Port
Among the projects, the high-voltage connection between Red Eléctrica's Cerdà substation and the Port substation stands out, which will enable, in a first phase, the expansion of the Nexigen Plan to electrify the main berths through new Onshore Power Supply (OPS) systems, allowing vessels to shut down their engines while berthed. This connection is considered a strategic milestone, as it grants the port an 80 MW allocation on the transmission grid, essential electrical capacity for advancing berth electrification.
Works at the Cerdà Substation
Red Eléctrica completed this summer the expansion works at the Cerdà 220 kV substation, with an investment of 37 million euros, according to details provided by Port de Barcelona and Diario del Puerto. The works also included the construction of three new lines -Cerdà-Hospitalet, Cerdà-Aeropuerto and Cerdà-Zona Franca-, all of which are now in service.
Next Steps
The Port substation will become operational in early 2027, enabling the commissioning of the first OPS system at a cruise terminal. The Port de Barcelona also plans to develop a green methanol plant to supply clean fuel for maritime transport, along with infrastructure for the hydrogen economy and the electrification of existing and future operations.
Statements
Redeia's chairwoman, Beatriz Corredor, noted that the collaboration with the Port de Barcelona will help lay the groundwork for a more sustainable, competitive and decarbonized port model, highlighting that the connection between the Cerdà and Port substations is key to providing the port with the electrical capacity it needs. For his part, the president of the Port de Barcelona, José Alberto Carbonell, stated that decarbonizing port operations means electrifying every possible process, and that Red Eléctrica is the key partner for this transformation, together with the installation of photovoltaic panels at the ZAL and other areas within the port.
Más destacadas
Holland America Opens Bookings for First Voyages of Revamped OosterdamHolland America Line has opened bookings for five new voyages aboard the Oosterdam, set to begin on October 31, 2027, following the ship's Evolution transformation in Marseille, France, which will add new suites and spaces such as the Grand Dutch Café.
Galveston Approves Modular LNG Plant on Pelican Island with Power LNGThe Galveston Wharves Board approved a lease agreement with Power LNG to build a modular LNG production, storage and bunkering facility on Pelican Island, with an initial capacity of 400,000 gallons per day and commercial startup expected in the fourth quarter of 2028.
Golar LNG Buys Grace Dahlia Carrier for Its Fourth MkII-Type FLNGGolar LNG has acquired the LNG carrier Grace Dahlia, the world's largest Moss-type vessel, to convert it into its fourth FLNG unit, the second of MkII design, ordered in August from CIMC Raffles in China with delivery expected in 2029.
APM Terminals Callao to Invest US$231 Million in New Berth 5CAPM Terminals Callao will build Berth 5C, measuring 440 meters long and 16 meters deep, with an investment of US$231 million. The project, expected to be completed by January 2028, will expand the North Terminal's capacity to 1.7 million TEU per year, with potential for up to 2.2 million.