Port of Barcelona Launches Tender to Electrify Ships with OPS System
Cubierto por 4 fuentesPublicado
- El Port de Barcelona convoca concurso para crear una sociedad que construya y explote la red de suministro eléctrico a buques
- Puerto de Barcelona licita concesión para una sociedad de suministro eléctrico a buques
- Port de Barcelona creará una sociedad para construir y explotar la red de suministro eléctrico a buques
- Barcelona targets 2027 for first cruise shore power connections
- Port de Barcelona apuesta por un modelo público-privado para construir y explotar el OPS
The Board of Directors of the Port de Barcelona approved launching a public tender to award a concession for the design, construction, operation and maintenance of the shore power supply service for vessels through Onshore Power Supply (OPS) systems, which allow ships to shut down their engines while berthed. The tender envisages a single concession company, 30% owned by the Port Authority of Barcelona, under a public-private partnership model.
Continuity of the works
The new company will carry forward the works already underway at the port, such as the Port substation and the rollout of medium-voltage and OPS networks at the quays, and will be responsible for completing infrastructure such as transformation and frequency conversion centers, ship connection systems, cable management, and control systems, in addition to operating and maintaining the network.
Investment under the Nexigen Plan
The initiative falls under the Port de Barcelona's Energy Transition Plan, which provides for a total investment of 1,700 million euros -780 million in public funds and 920 million in private capital- whose flagship project is the Nexigen Plan for quay electrification, with an investment of 215 million euros. Of that plan, the port has already executed or is executing 65 million euros, while the new company will have to cover the remaining 150 million euros, as also noted by Splash Cruise.
Timelines and cruise connections
The Port substation, connected to Red Eléctrica Española's Cerdà substation and with a capacity of 80 MW, will be operational in the first quarter of 2027. The first OPS systems for cruise ships will enter service that same year, with the connection at MSC Cruises' Terminal H, while the rest of the infrastructure at container, ferry and cruise terminals will be completed before 2030. Splash Cruise added that Barcelona has already awarded contracts worth 22.6 million euros to the Danish firm PowerCon for installations at the MSC Cruises terminal and at the future Terminal G, developed by Royal Caribbean Group and Cruise Terminals International, as part of a restructuring that will reduce the port's cruise terminals from seven to five.
Service already operational
According to Diario del Puerto, the OPS system is already operating at the BEST and Grimaldi terminals, giving continuity to the progress of the Nexigen Plan since its launch in 2022 and reinforcing the progressive electrification of the Port de Barcelona's quays.