Portonave Receives Two 55-Meter STS Cranes Amid Plan to Reach 2 Million TEUs
Cubierto por 3 fuentesPublicado
Portonave received two new 55-meter-tall electric ship-to-shore (STS) cranes on Saturday, November 14, manufactured by the Chinese company ZPMC. According to the terminal itself, the investment in the equipment totals R$ 229 million, a figure that Portal Portuario placed at around USD 40 million. The cranes are part of a plan to raise Portonave's annual container handling capacity from 1.5 million to 2 million TEUs.
Unloading and Technical Specifications
The cranes arrived welded to the vessel Zhen Hua 15, which had departed from Shanghai on September 21. Unloading requires a special operation that includes partially submerging the vessel by taking on river water as ballast, as well as installing beams over the quay rails and temporary mooring systems; the process is expected to take about five days. The fully electric cranes can lift loads of up to 100 tons and were designed to work vessels of up to 400 meters in length overall, in line with the growth of containerships on major international routes. Portonave expects to bring them into operation before December 31, after completing testing and staff training.
Berth Upgrade Works
The arrival of the cranes coincides with the completion of the berth upgrade works, which began in January 2024 and are part of an investment program exceeding R$ 2,000 million in infrastructure and technology. Once the process is finished, the terminal will have eight STS cranes and 32 RTG yard cranes, which will expand installed capacity by around 500,000 TEUs per year, a growth of approximately 33%. The cranes are part of a package worth more than R$ 500 million allocated to 100% electric equipment, which also includes the renewal of the yard fleet.
Draft Restrictions in the Itajaí Channel
Portonave's modernization is moving forward alongside draft restrictions in the access channel to the Itajaí port complex, which have already caused operational delays and reductions in vessels' cargo capacity. A technical report by Antaq, completed in October, recorded the case of the vessel MSC Pamela, which had to offload about 2,400 tons of refrigerated cargo because the authorized draft was 12.50 meters versus the 12.70 meters required. Portonave also reported to the agency delays of two hours 21 minutes and two hours 52 minutes in undocking maneuvers in February 2026, and estimated that each 10-centimeter reduction in depth can mean a loss of about a thousand tons of cargo per call, equivalent to around 40 containers.
Channel Concession Postponed
The concession project for the access channel infrastructure, which includes dredging and maintenance investments over 25 years and had already received approval from the Tribunal de Contas da União, was withdrawn from Antaq's agenda on November 12 at the request of the Ministério de Portos e Aeroportos, following objections from the Superintendência do Porto de Itajaí regarding the sedimentation volumes considered. In 2025, Portonave handled 1.03 million TEUs, a 14.5% decline compared to the previous year attributed to the upgrade works on one of its berths, while the Santa Catarina terminals as a whole handled 2.93 million TEUs, or 19.1% of the national total.
Más destacadas
Pilot Charged with Manslaughter Over Fatal Collision in Houston Ship Channel
Port of La Plata and CAF Explore Financing for Expansion Works
Tanker Atlantic Asphalt Collides With and Sinks Cruise Ship on Mississippi River After Steering Failure
Apache Workers' Strike in the North Sea Did Not Affect Production, Company Says