TCP Doubles Electrical Capacity at Paranaguá Terminal to 50 MVA
Cubierto por 2 fuentesPublicado
TCP, the company that operates the Paranaguá Container Terminal, completed on Sunday, November 22, the installation and commissioning of a second transformer at its electrical substation. The work is part of a R$7 million (USD 1.1 million) investment aimed at doubling the substation's transformation capacity, which rose from 25 to 50 megavolt-amperes (MVA), as part of the terminal's strategy to expand operations and reduce carbon emissions.
More Capacity for Reefers
The substation, inaugurated in 2023, had already been designed to house two 25 MVA transformers. With the installation of the second unit, the structure is now ready to support the increase in reefer container connection points, which will rise from the current 5,280 to 5,500 by the end of 2026 and to 6,000 in 2028. Kayo Zaiats, TCP's safety superintendent, noted that with cargo growth and the incorporation of new technologies, electricity demand tends to increase, and that the second transformer guarantees immediate improvements in quality and efficiency while also preparing the terminal to expand its operations.
Electrification of Cranes and Equipment
The new capacity is also key to the modernization of the terminal's equipment. It will enable the arrival of two new ship-to-shore (STS) gantry cranes scheduled for 2028 and will facilitate the replacement of diesel equipment with electric models. One of the main projects is the electrification of the fleet of 39 RTG cranes; three of them, operating in the rail yard, have already been converted, achieving a 97% reduction in greenhouse gas emissions, a 21% increase in productivity, and maintenance cost savings of up to 80% compared to diesel models. The expansion of the substation will allow progress on the electrification of the remaining 36 units.
Renewable Energy and Certifications
TCP has used electricity from renewable sources since 2021, which enabled it to obtain the international I-REC certificate for the fifth consecutive year in 2026. The company was also the first Brazilian port terminal to obtain ISO 50001 certification, focused on energy efficiency management. The sustainability strategy also includes the purchase of two electric buses, the replacement of forklifts with electric models at its import yard, and the evaluation of acquiring electric terminal tractors and heavy-duty electric forklifts.
Work Carried Out Without Interrupting Operations
The installation and commissioning of the second transformer were carried out with the substation in operation, requiring coordination among engineering teams to execute the work safely. During the works, cargo operations were partially maintained, avoiding a total shutdown of the terminal. After completing testing and verifying the safety and performance of the new equipment, the substation is now operating at its full planned capacity of 50 MVA.