The National Agency of Ports and Navigation (ANPYN) approved the public tender for the construction of a new catamaran pier for the Port of Ushuaia.
With an estimated budget of 12.580 million pesos, and a one-year duration, the tender, which will be published in the coming days, will increase the operational capacity of the Port of Ushuaia, improve the tourist experience, organize the catamaran embarkation and disembarkation system, and bring safety conditions to international standards.
The details of the tender were presented to the Fuegian private sector during an institutional visit to the Port attended by Patricio Cornejo, president of the Tierra del Fuego Chamber of Tourism, Juan Daniel González, head of the Ushuaia Chamber of Commerce and Other Business Activities, Andrea Forti, president of the Fuegian Association of Travel and Tourism Agencies (AAFUVYT) and Sales Manager of Rumbo Sur, María Laura Geuna, member of the AAFUVYT Board of Directors, Luis Di Giorgio, president of the Association of Tourism Hotels, and Guillermo García, president of the Tierra del Fuego Hotel and Gastronomic Chamber.
The new structure, with potential for expansion, will consist of a 120-linear-meter pier with availability on both sides, generating a usable surface of 240 meters, plus a 62-meter walkway over the water for passenger entry and exit.
The project seeks to solve one of the largest existing infrastructure deficits, providing a definitive solution to a long-standing sector demand. The project was announced on several occasions, but its budget was allocated to other purposes.
The current pier, meanwhile, had to be disabled after audits carried out by both ANPYN and specialized teams from the Navy and the Argentine Naval Prefecture, which confirmed the critical situation of its structure, being on the verge of new collapses and generating a risk to the lives of the thousands of passengers who transited it every day.
In this context, during the institutional tour, representatives of the private sector learned about the ongoing Works Plan and the repairs to the current catamaran pier, to reinforce its structure through driven piles, to recover stability conditions and enhance the existing structure.
Likewise, representatives of the provincial business, tourism, and economic chambers observed the progress of the works for the renovation and homogenization of all the main pier's defenses, which began in October and will continue during the season, without affecting operations.
The institutional visit also reviewed the ongoing tasks for the refloating of the Yerba-3 floating dock, and its subsequent transfer to a non-operational area, a task carried out together with the Argentine Navy, which will recover operational space at the pier.