The Port Authority expects to complete civil works by summer 2027 and all installations by the last quarter of the year
Cadiz, November 25, 2026. The Port Authority of the Bay of Cadiz (APBC) this week connected the two sections into which the access tunnel to the New Container Terminal (NTC) was previously subdivided. Over the last two and a half months, the remaining 150 meters of material separating both sections, approximately 10,000 m³, were excavated underground, achieving one of the main milestones in the complex execution of this strategic infrastructure for the development of the port of Cadiz. Work in this area must be completed by lowering the level of the excavation, where the reinforced concrete bottom slab of the structure will be executed.
The Port Authority visited the works this morning and confirmed that the tunnel is now connected along its entire length, which represents significant progress and allows the final stretch of the work to be tackled.
According to forecasts, civil works will be completed by summer 2027, and all tunnel installations will be executed in the last quarter of next year.
The road, which will connect the New Container Terminal with Astilleros Avenue, has a total length of 1.2 kilometers, of which 870 meters run through the tunnel, largely under the land granted by the Port Authority to Navantia Reparaciones Cádiz.
The connection of both tunnel sections is an especially significant milestone given the technical complexity of this infrastructure and the difficulties that have marked its execution since the start of works in November 2014.
It should be remembered that the Port Authority terminated the initial contract in June 2017 due to various problems that arose during its execution and after the previously constructed part of the tunnel was completely flooded.
Since May 2019, the APBC has carried out various actions aimed at recovering the infrastructure, repairing the water leaks that kept it flooded, emptying it, and stabilizing the parts of the structure that presented a risk of deterioration.
Likewise, the jet grouting treatment on the back of the screens and micropiles of the tunnel has been completed, with the aim of guaranteeing the durability of the structure and solving the pathologies derived from the construction defects of the first phase.
The works are now in their final phase, which includes the completion of civil works, interior paving, the execution of tunnel installations, surface road works to adapt to Navantia's infrastructure, and other necessary auxiliary works.
In parallel, the Port Authority is working on the remodeling of the Los Bomberos roundabout, where the tunnel entrance will be located, and which must adapt to both the new port connection and the future duplication of Industrial Avenue, to be executed by the City Council.
The construction of this tunnel access responds to the need to make the heavy vehicle traffic that the New Container Terminal will generate at full capacity compatible with the activity of the Cadiz shipyard.
Above the tunnel also runs the freight railway platform that will serve the new terminal, another of the strategic infrastructures to guarantee its competitiveness and enhance the intermodality of the Port of the Bay of Cadiz.
With the connection between the sections, the Port Authority overcomes one of the main constructive challenges of this project and takes a decisive step towards the completion of the land connectivity infrastructures of the New Container Terminal.