24 Nov 2026
Eight companies have submitted bids for the project design and technical assistance for the renovation of Raos 5 dock.
The contract, with a bidding budget of 803,125 euros, includes a fifteen-month execution period.
The president of the Port Authority of Santander (APS), César Díaz, stated that "the renovation of this dock is necessary to adapt its structural and operational capacity to an increased draft of up to 13 meters, thus facilitating greater versatility in the infrastructure's operation."
Santander, November 24, 2026. Once the bidding period concluded, eight companies submitted their offers for the drafting of the construction project and technical assistance for the renovation works of Raos 5 dock. The works have a bidding budget of 803,125 euros and a fifteen-month execution period.
The awarded company must draft the construction project within the first three months of the fifteen stipulated in the contract, while the remaining twelve months correspond to technical support for the construction management during its execution. As explained by the president of the APS, César Díaz, the decision to group both tasks responds to "the need to ensure continuity between the design phase and the subsequent supervision of a geotechnically and structurally complex project."
For Díaz, the renovation of this dock is necessary "to adapt its structural and operational capacity to an increased draft from 10 to 13 meters, thus facilitating greater versatility in the infrastructure's operation and increasing the Port's competitiveness."
During the project drafting, the awarded company must undertake preliminary work to verify available information and cartography, topographic and bathymetric surveys, and geotechnical campaigns, as well as the definition and calculation of the solution, dredging and environmental documentation, BIM -Building Information Modeling- methodology, and the presentation of a report including plans, budgets, a safety and health study, and waste management, among other things.
For its part, the phase of assistance to the construction management includes preliminary work before the start of the construction, on-site control, monitoring, and surveillance of the works, the safety and health coordination plan, as well as BIM technical assistance.
"We continue to reorganize spaces to improve the provision of port services at our public docks," he assured. This action, specifically, "complements the construction of the new Raos 6 dock, due to the significant increase in activity at the North Breakwater and the good progress of the container terminal," he pointed out.
Both interventions are included in the APS Investment Plan, which foresees public-private actions totaling 245 million euros until 2030. A figure that, according to the head of the port administration, includes "strategic projects" aimed at "meeting the current and future needs of the port" such as the vertical car silo or the new urban access to the port.
Likewise, Díaz reiterated the institution's commitment to the economic development of Cantabria, "supporting our industry through a strong and committed Port, capable of generating economic activity and employment in the region," he concluded.