Over the summer, we connected the Polish offshore wind farm Baltyk 2 to the mainland. We transported, installed and protected subsea export cables, enabling the transfer of renewable energy from sea to shore once the wind farm is operational. In 2027, we will return to carry out the same scope of work for the neighbouring Baltyk 3 wind farm.
Powering more than 2 million households
Baltyk 2 and Baltyk 3, developed by Equinor and Polenergia, will be among Poland's first operational offshore wind farms. Together, they will generate enough renewable energy to power more than 2 million households, marking a significant step forward in Poland's energy transition and energy security.
To bring this green energy ashore, we are working closely with our partner Hellenic Cables, responsible for the design and manufacturing of the subsea export cables.
From route preparation to cable protection
Our works on Baltyk 2, located 37 kilometres off the Polish coast, began in 2025 with the clearance of boulders along the cable routes, ensuring safe installation conditions. In June this year, our cable-laying vessel Isaac Newton started installing 120 kilometres of export cables along the prepared routes. The team completed the installation campaign by pulling in the cables to the offshore substation, preparing the connection of the wind farm to the Polish electricity grid.
To complete the works, our vessel Symphony and trencher Swordfish trenched the cables wherever possible, burying them beneath the seabed for long-term protection against external impacts.
Looking ahead to Baltyk 3
In 2027, we will return to Poland to connect the neighbouring Baltyk 3 offshore wind farm to the mainland.