APM Terminals obtained environmental approval from Senace to carry out new works at the North Dock of the Port of Callao.
APM Terminals Callao prepares plan to extend concession with investments outside the port
Just over a month before the end of 2026, APM Terminals, operator of the North Multipurpose Terminal of the Port of Callao and part of the A.P. Moller-Maersk group, received environmental authorization to carry out new works in this port infrastructure, with a view to adapting the facilities to the characteristics and dimensions of the vessels operating in the terminal. What works will it execute and within what deadlines?
In detail, the National Environmental Certification Service for Sustainable Investments (Senace) approved the Supporting Technical Report (ITS) presented by the company to modify the slope profiling of Dock 5C and the dredging works corresponding to the third stage of modernization of the terminal.
With this approval, the concessionaire has the environmental certification to carry out the planned works in the Port of Callao. The authorization was issued on November 10 and had the favorable opinion of the National Water Authority (ANA).
What works will APM Terminals carry out?
The approved ITS explains that the project includes interventions in two areas of the terminal. One of them is Central Dock No. 4, where the company will increase the dredging depth from 12 to 13.80 meters. In addition, it will build a transition zone between the docks to gradually connect the different depths.
The second intervention will be carried out at Dock 5C. At this point, APM Terminals will carry out excavation works at the base of the slope to reinforce the protection of the structure with rocks. This intervention will reach a depth of 19.30 meters, although the operational depth of the dock will remain at 16 meters.
The works will also involve an adjustment in the amount of material to be removed from the seabed. The extracted material, the document notes, will be transferred to the marine deposit that already has authorization to receive these residues.
How much will it invest and how long will the works take?
To carry out these interventions, APM Terminals will allocate US$ 13.8 million. Of that total, US$ 153,808 will be used for environmental management measures, which include water and sediment monitoring, as well as the use of equipment to reduce particle dispersion during the works.
Regarding the deadline, the activities will require 151 days of work: 106 days for dredging, 35 days for slope conditioning, and 10 days for seabed measurements. These periods do not include the time necessary to transfer vessels and equipment to the work area.
The general schedule establishes five months for interventions at Dock 5C, Dock 4, and the access channel, while works at Central Docks No. 1 and No. 2 will have a period of four months.
Before starting the works at sea, APM Terminals Callao must process the corresponding sectoral licenses and permits. It will also have to communicate the start of the works to Senace and the entity responsible for environmental oversight.