25/11/2026 - 10:00

PortosRio began complementary mixed geotechnical soundings in the Commercial Channel of the Port of Rio de Janeiro, next to Gamboa Wharf, last Friday (11/20). The services are part of the channel dredging contract execution and will be carried out exclusively at night until January 13, 2027.

The soundings continue previous surveys and will allow for the completion of soil characterization, which will serve as the basis for the executive project. Dredging is scheduled to begin in the first quarter of 2027.

The project covers the access channel to Gamboa Wharf and berths 100 to 125. The planned depth is 13 meters, with a dredging tolerance of up to an additional 0.50 meter.

The intervention aims to adjust the depth to the needs of vessels operating in the port, contributing to navigation safety and the efficiency of port operations.

The services will be carried out at night to minimize impacts on waterway traffic and port operations. During the surveys, temporary channel closures are expected and will be announced in advance to ensure the safety of navigation and the teams involved.